GreenYard Properties Development

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 22 Nov 2026.

Under construction

0

Units

0

Delivered (all years)

3

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
0
Promised for 2027
0
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 13 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 21.46M
31 sales
–
AED 21.78M
27 sales
2026 so far
AED 15.81M
23 sales
–
AED 19.49M
23 sales
2025
AED 43.94M
54 sales
–
AED 33.05M
44 sales
2024
AED 32.27M
28 sales
–
AED 36.30M
44 sales
2023
AED 255.58M
414 sales
–
AED 44.41M
70 sales
2022
AED 5.15M
9 sales
–
AED 16.19M
25 sales
2021
AED 140.25M
302 sales
–
AED 8.40M
14 sales

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Joya Verde Residences DubaiDelivered100%Jan 2019Jan 2019
Joya Blanca ResidencesDelivered100%Sept 2022Sept 2022
Joya Dorado ResidenceDelivered100%Mar 2025Mar 2025