Green Emirates Co.Psc
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 22 Nov 2026.
Under construction
0
Units
0
Delivered (all years)
1
Behind schedule
0
Cancelled (all years)
4
Promised for 2026
0
Promised for 2027
0
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 13 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | – | – | AED 51.11M 20 sales |
| 2026 so far | – | – | AED 47.76M 18 sales |
| 2025 | – | – | AED 42.24M 26 sales |
| 2024 | – | – | AED 27.40M 20 sales |
| 2023 | – | – | AED 47.08M 44 sales |
| 2022 | – | – | AED 25.56M 30 sales |
| 2021 | – | – | AED 8.42M 16 sales |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Clover Bay | Delivered | 100% | Oct 2011 | Oct 2011 | |
| Bay View Residences | Cancelled | 0% | – | – | |
| Silver Bay | Cancelled | 0% | – | – | |
| New Port Tower | Cancelled | 0% | – | – | |
| Burj Al Noor | Cancelled | 0% | Jan 2011project register | Jan 2011 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.