Fortune 5
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
0
Units
0
Delivered
1
Behind schedule
0
Cancelled
1
Handovers 2026
0
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 25 Sept 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | – | – | AED 34.52M 17 sales |
| 2026 | – | – | AED 22.83M 12 sales |
| 2025 | AED 23.49M 13 sales | – | AED 11.69M 5 sales |
| 2024 | AED 59.21M 33 sales | – | – |
| 2023 | AED 164.04M 92 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| West Five Business Bay Residences | Delivered | 100% | Dec 2024 | Dec 2024 | |
| Orchid Residence | Cancelled | 26% | Jul 2027 | Jul 2027 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.