Dar Global
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
4
Units
1,405
Delivered
1
Behind schedule
0
Cancelled
0
Handovers 2026
1
Handovers 2027
1
Handovers 2028
1
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| City Center Residences | Slower than needed | 72% | Sept 2026 | Sept 2026 | |
| Dg1 Living | Slower than needed | 53% | Apr 2027 | Apr 2027 | |
| D Villas | Early stage | 9% | Dec 2028 | Dec 2028 | |
| Trump Tower | Early stage | 4% | Dec 2031 | Dec 2031 | |
| Urban Oasis | Delivered | 100% | Jun 2024 | Jun 2024 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.