City View

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

2

Units

652

Delivered

0

Behind schedule

0

Cancelled

0

Handovers 2026
0
Handovers 2027
1
Handovers 2028
1
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
City View Dubai Hills ResidencesSlower than needed39%Mar 2027Mar 2027
Velos ResidenceEarly stage7%Jun 2028Oct 2028 4 months later on DLD than advertised