Amer Alghurair Co
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.
This developer has 2 project(s) in the register, too few for a track record: read the counts as single projects.
Under construction
2
Units
1,483
Delivered (all years)
0
Behind schedule
1
Cancelled (all years)
0
Sales in this developer's projects
Registered sales by period; the latest figures run to 11 Nov 2026.
| Period | Off-plan sales | Villa plots sold on plan | Resales in completed projects |
|---|---|---|---|
| Last 12 months | AED 214.36M 264 sales | – | AED 73.47M 70 sales |
| 2026 so far | AED 195.12M 240 sales | – | AED 54.19M 54 sales |
| 2025 | AED 121.80M 135 sales | – | AED 51.82M 47 sales |
| 2024 | AED 4.26M 6 sales | – | – |
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Living Legends Phase 5 | Behind schedule | 49% | Mar 2025project register | Mar 2025 | 20 months past promised handover |
| Living Legends Phase 4 | Slower than needed | 62% | Mar 2027project register | Mar 2027 |
Amer Alghurair Co: questions and answers
How many projects is Amer Alghurair Co building in Dubai?
Amer Alghurair Co has 2 projects under construction in Dubai, with 1,483 homes in total, according to the Dubai Land Department project register.
When do Amer Alghurair Co projects hand over?
Handover years for Amer Alghurair Co's projects under construction, by the developer's date where it gave one, else the date in new-project listings, else the Dubai Land Department project register's date: 1 project in 2027.
How far is construction of Amer Alghurair Co's projects?
Among Amer Alghurair Co's projects under construction, the most advanced are Living Legends Phase 4 (62% built) and Living Legends Phase 5 (49% built), from official RERA site inspections.
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.