Amer Alghurair Co
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
2
Units
1,483
Delivered
0
Behind schedule
1
Cancelled
0
Handovers 2026
0
Handovers 2027
1
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| Living Legends Phase 5 | Behind schedule | 49% | Mar 2025 | Mar 2025 | 18 months past promised handover |
| Living Legends Phase 4 | Slower than needed | 62% | Mar 2027 | Mar 2027 |
✦ Ask about any developer
Track record, projects handing over by year and construction progress — from official records.