← All developers

Alaia Developments

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date. Project register as of 15 Nov 2026.

This developer has 1 project(s) in the register, too few for a track record: read the counts as single projects.

Under construction

1

Units

59

Delivered (all years)

0

Behind schedule

0

Cancelled (all years)

0

Promised for 2026
0
Promised for 2027
1
Promised for 2028
0
Promised for 2029
0
Promised for 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 11 Nov 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months
AED 37.77M
21 sales
––
2026 so far
AED 35.94M
20 sales
––
2025
AED 35.93M
19 sales
––

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Chelsea GardensEarly stage10%Jun 2027Developer statesFeb 2027