Allegro Residences
by Abra Group
Allegro Residences is a project by Abra Group in Dubai. The Dubai Land Department project register lists completion for April 2026. It was 77% built at the official RERA site inspection of 4 August 2026.





About the project
Sold-out residential project.
Construction progress
77.49% complete at the latest RERA site inspection on 4 Aug 2026; scheduled completion 7 Apr 2026.
| Inspection | Complete | Photos |
|---|---|---|
| 4 Aug 2026 | 77.49% | 10 |
| 7 May 2026 | 70.03% | 10 |
| 5 Mar 2026 | 56.27% | 11 |
| 26 Nov 2025 | 34.61% | 9 |
| 4 Aug 2025 | 17.84% | 5 |
| 17 Mar 2025 | 6.1% | 4 |
| 29 Nov 2024 | 0% | 2 |
Escrow account 1091226129725002 at First Abu Dhabi Bank P.J.S.C.. Payments for units in this project go into this account.
Official RERA site-inspection records for registered project #3404, updated daily. Tap a photo for the full-size original.
Who's selling this project
1 agency is currently listing units in Allegro Residences across 1 live listings, from AED 2.00M to AED 2.00M depending on unit size and floor.
| Agency | Listings | Asking range | Trust |
|---|---|---|---|
| Homify Properties | 1 | AED 2.00M | 1 verified · TruBroker |
Live asking prices from agency listings — compare before you commit. Ranges span different unit types and floors, and asking prices are not sold prices.
Allegro Residences: questions and answers
When is the handover of Allegro Residences?
The Dubai Land Department project register lists the completion date of Allegro Residences as April 2026.
How much of Allegro Residences is built?
Allegro Residences was 77% complete at the official RERA site inspection of 4 August 2026.
Is Allegro Residences registered with the Dubai Land Department?
Yes. Allegro Residences is registered with the Dubai Land Department as project number 3404, and its escrow account is held at First Abu Dhabi Bank P.J.S.C.. By law, buyers' payments for an off-plan home in Dubai go into the project's escrow account.
Who is the developer of Allegro Residences?
Allegro Residences is developed by Abra Group. The Dubai Land Department project register lists 6 projects for Abra Group: 1 delivered and 5 under construction.
What unit types does Allegro Residences offer?
The project has 60 units in the Dubai Land Department project register.
Explore more
More off-plan projects by Abra Group
✦ Want the full picture on Allegro Residences?
This page shows what we collected. Ask the AI to compare it against other projects, run the rental ROI and mortgage numbers, or check how its area is performing on real DLD sales.
Source: developer’s official website + live listing photos. Prices are "starting from" figures where published. Always verify with the developer before transacting. Project details last checked on 4 Aug 2026.