Damac Star

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

0

Units

0

Delivered

12

Behind schedule

0

Cancelled

0

Handovers 2026
0
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Sales in this developer's projects

Registered sales by period; the latest figures run to 25 Sept 2026.

PeriodOff-plan salesVilla plots sold on planResales in completed projects
Last 12 months––
AED 556.50M
371 sales
2026––
AED 362.25M
237 sales
2025––
AED 698.38M
472 sales
2024––
AED 693.14M
494 sales
2023––
AED 649.62M
449 sales
2022––
AED 626.42M
408 sales
2021––
AED 344.44M
277 sales

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
The Residence At Business CentralDelivered100%Feb 2013Feb 2013
The SignatureDelivered100%May 2013May 2013
Park CentralDelivered100%Nov 2013Nov 2013
Water'S EdgeDelivered100%Dec 2013Dec 2013
Executive Bay ADelivered100%Mar 2014Mar 2014
Executive Bay BDelivered100%Mar 2014Mar 2014
The CosmopolitanDelivered100%Mar 2014Mar 2014
Capital Bay ADelivered100%Mar 2014Mar 2014
Capital Bay BDelivered100%Apr 2014Apr 2014
The VogueDelivered100%Jun 2014Jun 2014
Damac Towers By ParamountDelivered100%Oct 2018Oct 2018
Avanti TowerDelivered100%Dec 2018Dec 2018