CONTINENTAL INVESTMENTS LMD L. L. C
Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.
Under construction
4
Units
1,108
Delivered
5
Behind schedule
4
Cancelled
0
Handovers 2026
4
Handovers 2027
0
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0
Projects
% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.
| Project | Status | Built | Handover date | DLD planned date | Note |
|---|---|---|---|---|---|
| The Pier | Behind schedule | 35% | Mar 2026 | Dec 2026 | 6 months past promised handover 9 months later on DLD than advertised |
| Boutique 23 | Behind schedule | 49% | Mar 2026 | – | 6 months past promised handover |
| Taiyo Residences | Behind schedule | 5% | Mar 2026 | Dec 2027 | 6 months past promised handover 21 months later on DLD than advertised |
| La Boutique | Behind schedule | 38% | Mar 2026 | Dec 2026 | 6 months past promised handover 9 months later on DLD than advertised |
| Continental Tower | Delivered | 100% | Apr 2017 | Apr 2017 | |
| Rukan2 | Delivered | 100% | Aug 2022 | Aug 2022 | |
| Rukan 3 | Delivered | 100% | Dec 2022 | Dec 2022 | |
| Rukan | Delivered | 100% | Jan 2023 | Jan 2023 | |
| Marina Living | Delivered | 100% | Jun 2025 | Jun 2025 |