Andalusia Group

Projects from the official DLD/RERA project status, updated daily. Promised handover = the developer's advertised date where we have it, otherwise DLD's planned date.

Under construction

1

Units

60

Delivered

2

Behind schedule

0

Cancelled

0

Handovers 2026
0
Handovers 2027
1
Handovers 2028
0
Handovers 2029
0
Handovers 2030
0

Projects

% built is from the latest RERA site inspection. “On schedule” and “Slower than needed” compare the recent construction pace with the time left to the promised handover — an indication, not a certainty. For delivered projects the completion date is shown.

ProjectStatusBuiltHandover dateDLD planned dateNote
Bottega Nove By LalavSlower than needed30%Jul 2027Jul 2027
Maya TownhousesDelivered100%Jul 2023Jul 2023
Maya Luxury CollectionDelivered100%Mar 2025Mar 2025